Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What ef…

Your schedule has a critical path of tasks A-D-E-F. A team
member tells you that task B, which was originally planned to take
6 days with 5 days of float, has been re-estimated to take 9 days.
What effect would you expect this to have on the schedule?

Select one:

a. Task B would have 1 day of lag

b. The project completion date would be increased by 3 days.

c. Task B is now part of the critical path

d. The critical path would still be A-D-E-F